17.62.210 Use of elevation certificates.
Lindon City may require that the following elevations certificates be completed for any new residential or nonresidential building construction within the special flood hazard area (SFHA):
1. Proposed Conditions. A proposed conditions elevation certificate is required to be completed by a professional and licensed engineer, surveyor, or architect as part of the floodplain permit package;
2. Building Under Construction. A building under construction elevation certificate is required to be completed by a professional and licensed engineer, surveyor, or architect after foundation has been poured; and
3. Finished Construction. A finished construction elevation certificate is required to be completed by a professional and licensed engineer, surveyor, or architect once the structure is completed, utilities are installed, and grading and landscaping have been completed. (Ord. 2020-7 §1, amended, 2020)