a. Prior to beginning work, developers and contractors must provide appropriate instruction to on-site construction supervisors and operators, regarding the requirements of the Construction Site Storm Water Management Plan. A copy of the plan must be present at the construction site.

b. The improvements shown in the approved Construction Site Storm Water Management Plan must be construction as indicated in the plan. The appropriate activities outlined in the Construction Site Storm Water Management Plan must be constructed as Management Plan must be performed prior to any other construction activities on the site. Lindon City encourages modifications to the plan when needed to improve storm water management in light of site condition, but any variation from the approved plan that reduces or eliminates any element of the plan must first be approved by the Lindon City Public Works Representative or City Engineer.

c. After initial implementation of the improvements outlined in the approved Construction Site Storm Water Management Plan, precipitation activity will provide opportunity to observe the effectiveness of the storm water management improvements. Those responsible for construction activities must monitor the in-place storm water management improvements to assess their effectiveness; they must then make adjustments to the improvements as needed to accomplish effective storm water management. The City shall be entitled to monitor the effectiveness of the Construction Site Storm Water Management Plan and to require modifications to the plan as is necessary to achieve the purposes of this chapter.

d. Verification that improvements were constructed as approved.

1. Following implementation of the improvements contained in the Construction Site Storm Water Management Plan, the preparer of the plan shall provide Lindon City with a statement as to the condition of the improvement contained in the plan. The statement shall be made on a copy of the Construction Site Storm Water Management Plan document, and shall be signed.

2. If the improvements were constructed as approved, the statement shall include language verifying such. If the improvements were not constructed as approved, it shall state the differences, the reason for the differences, the reason for the differences, and provide an opinion as to the adequacy of the constructed improvements. This statement must be provided to Lindon City prior to final acceptance of improvements (in the case of public improvements) or issuance of an occupancy permit (in the case of private site improvements).